30AprReducer size calculationD=m z/c o sɑ=3×3 5/cos19.5283°=111.4mm. According to previous experience, the maximum speed of the servo motor is initially selected Nmax=3 000r/min,
view more
29JunCalculation of reducer sizei is the planetary reducer deceleration Ratio; D is the index circle diameter of the output gear meshing with the rack, in mm; v fast is the fast forw
view more
29AprSelection and calculation of the reduction ratio of the reducer.Selection and calculation of the reduction ratio of the reducer. Initially determine the reduction ratio i according to the fast forward speed, (Nmax/
view more
29Aprthe scrap must be clarified in advanceSometimes the price of the processed scrap is calculated when the star rating is too big. If it is non-ferrous metals, the scrap must be clarified in
view more
29AprThat is not a small incomeThat is not a small income. The calculation method of the unit price of the workpiece processed by the lathe 1. The outer diameter of the first car On
view more
29AprAssuming that the speed is 120 rpm and the feed is 01mmAssuming that the speed is 120 rpm and the feed is 01mm, then the time of one cut can be calculated as 24÷(120×0.1) about 2mn (24 workpieces 20 + retr
view more
29AprThe second step is a car buckleThe second step is a car buckle. The M16 thread is 2mm pitch, so the length of 20 is 10 laps, plus the tail-out width is at least 12 laps. If it is 60
view more
29AprHalf of the minute is 0.1 minutesHalf of the minute is 0.1 minutes. Adding up the screw thread is 0.3 minutes per cut. This coarse threading is four-knife fine-cutting-one-cut is 0.3×
view more
29AprThe third step is cuttingThe third step is cutting. If the feed rate is 0.1 revolutions, 100 revolutions per minute is calculated, which is 16÷(100×0.1)=1.6 minutes Pride is d
view more
29AprThe above working hoursThe above working hours are 2+1.5+1.6=5.1 minutes in total; if it is a single piece, add the auxiliary time 30 minutes=35.1 minutes; if the batch size
view more
29Aprcalculated by CNC 30 yuan/hourcalculated by CNC 30 yuan/hour Single piece 35.1×(30÷60)=17.55 yuan/piece; batch 500 pieces: 6×(30÷60)=3 yuan/piece material + processing man-hour) *1
view more
29AprNext is the hourly rateNext is the hourly rate, processing man-hour should be converted into Money is calculated like this here. Every place is different; 1.3 is 30% profit
view more